PH luxury interiors pre-opening checklist (2026)
Method only. Public facts. No named live job, no room count, no invented date.
Strike a line only when the work is done — not when it is promised.
1. Wet and services
- Wet areas closed, fallen, and water-tested (guest, F&B, staff)
- Ceiling services signed on guest floors and corridors
- Access panels cut to drawing
- Fire and life-safety interfaces named (who closes, who certifies)
2. Envelope and joinery
- Walls true before stone / millwork templates
- Brand-nominated series listed with a written equivalent rule
- Owner-procured vs contractor-supplied split frozen (buyer / installer / warrantor)
- OSM receiving slot named (day, store, counter) — not the driveway
3. Protection and loose FF&E
- Corridor protection in before the first loose crate
- Furniture delivery refused if ceilings are open
- Unpack list on every owner crate
- Room set before corridor set; F&B rooms after kitchen plant is still
4. Outdoor / marine-leisure (if the asset has it)
- Deck and drain before loose outdoor pieces
- Salt / weather exposure named on finishes
- Outdoor fabric after wet trades — not before
5. Close
- Snag is a close-out, not a second programme
- One named weekly that walks this list